Title: To authorize the transfer and appropriation of funds within the Sidewalk Assessment Fund; to authorize the Director of Public Service to enter into a contract modification with Decker Construction Company in connection with the Pedestrian Safety Improvement - Sidewalk NOV Program 2021 project; to authorize the expenditure of up to $158,385.50 from the Sidewalk Assessment Fund for the project; and to declare an emergency. ($158,385.50)
Attachments: 1. ord 2474-2021 accounting template
Explanation
1. BACKGROUND
This ordinance authorizes the Director of Public Service to modify and increase an existing contract with Decker Construction Company for the Pedestrian Safety Improvement - Sidewalk NOV Program 2021 project in an amount up to $137,726.60 and to add funding for additional construction administration and inspection costs in an amount up to $20,658.90.
Ordinance 1861-2021 authorized the Director of Public Service to enter into a contract with Decker Construction Company for the construction of the Pedestrian Safety Improvement - Sidewalk NOV Program 2021 project and to provide for construction administration and inspection services. This project consists of the repair or replacement of damaged or deteriorated sidewalk, drive approach, or curb within the public right-of-way at various pre-determined locations throughout the City. Under City Code it is the property owner’s responsibility to repair or replace these items. Public Service sends a notice of violation to the property owner notifying them they need to make the repairs or the City will make the repairs and charge the property owner. This contract will make repairs on any properties for which the property owner does not make the repairs.

Since the bid award it has been determined more work is required to repair the locations than was advertised in the bid documents. Modification 1 will add funding to the contract to allow for full funding of all repairs needed for all of the properties on the original repair list.

The original contract amount: $114,097.50 (PO284587, Ord. 1861-2021)
The total of Modification No. 1: $137,726.60 (This Ordinance)
The contract amount including all modifications: $251,824.10

Searches in the System for Award Management (Federal) and the Findings for Recovery list (State) produced no findings against Decker Construction Company.

2. CONTRACT COMPLIANCE
The contract com...