Title: To amend the 2021 Capital Improvement Budget; to authorize the transfer of funds and appropriation within the Streets and Highways Bond Fund; to authorize the Director of Public Service to enter into a contract modification with Arcadis US Inc., in connection with the UIRF - Milo Grogan Second Avenue Improvements project; to authorize the expenditure of up to $70,000.00 from the Streets and Highways Bond Fund for the project; and to declare an emergency. ($70,000.00)
Attachments: 1. ORD 3111-2021 Accounting Templates.pdf
Explanation
1. BACKGROUND
This ordinance authorizes the Director of Public Service to modify a professional services contract with Arcadis US Inc., to add additional funds of $70,000.00 for design of the UIRF - Milo Grogan Second Avenue Improvements.
Ordinance 0465-2017 authorized the Director of Public Service to enter into a professional services contract with Arcadis US Inc., for the UIRF - Milo Grogan Second Avenue Improvements project. The contract is to produce construction plans and associated deliverables for improvements to East Second Avenue from Sixth Street to St. Clair Avenue. Improvements will generally consist of new pervious pavement in the parking lane of 2nd Avenue, resurfacing the remaining existing pavement, replacing the existing curb and installation of curb extensions to define the parking areas. Streetscape improvements will consist of replacement of existing sidewalks, new street trees, and new street lighting with underground circuit. The signals at Cleveland Avenue and St. Clair Avenue will be modified to accommodate the proposed improvements.

Ordinance 2933-2018 authorized the Director of Public Service to modify the contract due to expanding the scope of the project to include the City-owned retaining walls that are adjacent to the project area and assigning detailed design work.

This is a planned modification that is necessary to cover the cost of work to include additional right of way, stormwater, and utility design services. It was deemed to be more cost efficient to modify the existing contract than to bid this part of the work.

The original contract amount: $400,000.00 (PO074422, Ord. 0465-2017)
The total of Modification No. 1: $264,000.00 (PO152651, Ord. 2933-2018)
The total of Modification No. 2: $ 70,000.00 (This ordinance)

The contract amount including all modifications: $734,000.00

Searches in the System for Award Management (Federal) and the Findin...