Title: To authorize the Director of Public Utilities to enter into a construction contract with General Temperature Control, Inc. for the JPWWTP SCB HVAC UNIT H25 Replacement; to authorize the transfer within of $340,800.00 and the expenditure of up to $340,800.00 from the Sanitary Sewer General Obligation Bond Fund; and to amend the 2021 Capital Improvements Budget. ($340,800.00)
Attachments: 1. 0046-2022 Funding Template, 2. 0046-2022 Utilization Form, 3. Director's Legislation Information Sheet 650265-100112

Explanation

 

BACKGROUND: This legislation authorizes the Director of Public Utilities to enter into a construction contract with General Temperature Control, Inc. for the JPWWTP SCB HVAC Unit H25 Replacement, 650265-100112. This is a contract for the complete HVAC removal and replacement of the Jackson Pike Wastewater Treatment Plant SCB HVAC UNIT H25.   Work under this project consists of replacement of the SCB Building HVAC unit 25, and other such work as may be necessary to complete the contract, in accordance with the drawings, technical specifications, and City of Columbus Construction and Material Specifications as set forth in this Invitation For Bid (IFB).

 

 

Planning area: 59 Southwest

 

PROJECT TIMELINE: All work shall be substantially complete within 300 (three hundred) calendar days of the Notice to Proceed, with final completion to occur within 330 (three hundred thirty) calendar days. 

 

PROCUREMENT INFORMATION: The Division advertised for competitive bids submission for the subject services on the City's Vendor Services website and in the City Bulletin in accordance with the overall provisions of Chapter 329 of the Columbus City Code. The Division of Sewerage and Drainage received three (3) bids on December 15, 2021 from the following companies:

 

NAME

TAX ID

DAX #

City/State

Status

Expiration

General Temperature Control

31-1201236

004830

Canal Winchester,  OH

MAJ

9/30/2022

The Righter Co., Inc.

31-0889208

004433

Columbus, OH

MAJ

11/22/2023

 

 

 

 

 

 

DeBra-Kuempel, Inc.

31-1615931

005675

Cincinnati, OH

MAJ

12/18/2022

 

DeBra-Kuempel, Inc. submitted an incomplete bid and was deemed ineligible.  Therefore, General Temperature Control, Inc. was awarded the project based on the Bid Tabulation and Quality Factor Form evaluation process results. 

 

EMERGENCY DESIGNATION is not requested for this project.

 

CONTRACT COMPLIANCE NO: 31-1201236 | Exp. 09/30/2022 | MAJ | Vendor # 004830

ECONOMIC / ENVIRONMENTAL IMPACT: Many of the HVAC & air purification units are approaching the end of their useful life and are becoming increasingly difficult to repair and maintain. A DOSD replacement program was developed under CIP 650265-100100.  Replacement of failing HVAC & air purification units will provide proper environmental controls for essential process equipment, electrical equipment, furnishings, structures and documents.  The replacement units will help to extend the useful life of the building and all equipment inside and inhibit deterioration.

.

FISCAL IMPACT: This legislation authorizes the transfer within of $340,800.00 and expenditure of up to $340,800.00, which includes $2,000.00 for Prevailing Wage fees from the Sanitary Sewer General Obligation Bond Fund 6109 and amends the 2021 Capital Improvements Budget.

 

Title

 

To authorize the Director of Public Utilities to enter into a construction contract with General Temperature Control, Inc. for the JPWWTP SCB HVAC UNIT H25 Replacement; to authorize the transfer within of $340,800.00 and the expenditure of up to $340,800.00 from the Sanitary Sewer General Obligation Bond Fund; and to amend the 2021 Capital Improvements Budget. ($340,800.00)

 

Body

 

WHEREAS, the Division of Sewerage and Drainage advertised for competitive bids for HVAC removal and replacement for the JPWWTP SCB HVAC UNIT H25 Replacement Project, 650265-100112, three (3) bids were received; and 

 

WHEREAS, it was determined that General Temperature Control Inc. should be awarded the project based on the results of the Bid Tabulation and Quality Factor Form evaluation; and 

 

WHEREAS, it is necessary to authorize the transfer within and the expenditure of up to $340,800.00 from the Sanitary Sewer General Obligation Bond Fund, Fund 6109; and

 

WHEREAS, $2,000.00 of the project cost is for Prevailing Wage Services to the Department of Public Service; and

 

WHEREAS, it is necessary to authorize the amendment to the 2021 Capital Improvements Budget to provide sufficient budget authority; and

 

WHEREAS, it has become necessary in the usual daily operation of the Department of Public Utilities, Division of Sewerage and Drainage, to authorize the Director to enter into a construction contract with General Temperature Control, Inc., for the JPWWTP SCB HVAC UNIT H25 Replacement, 650265-100112, for the immediate preservation of the public health, peace, property and safety; now, therefore

 

BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:

 

SECTION 1: That the Director of Public Utilities is hereby authorized to enter into a construction contract with General Temperature Control, Inc., 970 W. Walnut St. Canal Winchester, OH 43110 for the JPWWTP SCB HVAC UNIT H25 Replacement, 650265-100112, in accordance with the terms and conditions of the contract on file in the Office of the Division of Sewerage and Drainage.

 

SECTION 2. That the transfer of $340,800.00 is hereby authorized in the Sanitary Sewer General Obligation Bond Fund 6109 per the accounting codes attached to this ordinance.

 

SECTION 3. That the expenditure of up to $338,800.00 or as may be needed, plus $2,000.00 for Prevailing Wage fees, is hereby authorized per the accounting codes in the attachment to this ordinance.

 

SECTION 4. That the 2021 Capital Improvements Budget is hereby amended per the accounting codes attached to this ordinance.

 

SECTION 5. That the said firm, General Temperature Control, Inc., shall perform the work to the satisfaction of the Director of Public Utilities and the Administrator of the Division of Sewerage and Drainage.

 

SECTION 6. That the City Auditor is hereby authorized and directed to transfer any unencumbered balance in the project account to the unallocated balance within the same fund upon receipt of certification by the Director of the Department administering said project that the project has been completed and the monies no longer required for said project; except that no transfer shall be made from a project account by monies from more than one source.

 

SECTION 7. That the City Auditor is authorized to establish proper project accounting numbers as appropriate.

 

SECTION 8. That the City Auditor is authorized to make any accounting changes to revise the funding source for all contracts of contract modifications associated with this ordinance.

 

SECTION 9. That the funds necessary to carry out the purpose of this ordinance are hereby deemed appropriated, and the City Auditor shall establish such accounting codes as necessary.

 

SECTION 10. That this ordinance shall take effect and be in force from and after the earliest period allowed by law.