BACKGROUND: This Engineering Agreement is necessary to provide overall engineering services to the Division of Sewerage and Drainage on an “as-needed” basis for work on the sanitary and storm sewer systems. The actual detailed design, construction, and inspection of improvements in the sewer collection systems will generally be accomplished by others. Overall Engineering Consultant Services (OEC) are necessary to provide technical and engineering assistance to the City and its design professionals in planning and coordination of the work. The OEC services are separated into several tasks, as follows:
Task 1 - Planning Services
Task 2 - Design Services
Task 3 - Construction Related Services
Task 4 - General and Additional Services
Task 5 - Project Management
The Community Planning Area is 99 - Citywide
PROCUREMENT: The Department of Public Utilities advertised a Request for Proposals (RFP’s) for Sewer Collection System - Overall Engineering Consultant (OEC) 2022-2024 #650025-100001 on the Vendor Services and Bonfire websites that closed on November 19, 2021. The city received one (1) response from the following firm: Hazen and Sawyer. All proposals were evaluated in accordance with Columbus City Code Title 3, Chapter 329.28, and were scored according to competence to perform, past performance, and understanding of the project approach.
MULTI-YEAR CONTRACT: The Department anticipates requesting additional future renewals to this contract.
PROJECT TIMELINE: This contract is planned for renewals and will span multiple years, concluding in 2024.
Contract Compliance No.: 13-2904652 | MAJ | 03/05/2022 | Vendor#: 000630
Emergency Designation: Emergency legislation is not requested at this time.
Economic Impact: The project provides many metrics on various environmental factors that are noted in the work to be performed. The information provided assists and guides the City in decision making on environmental issues....