File #: 0294-2022    Version: 1
Type: Ordinance Status: Passed
File created: 1/19/2022 In control: Public Utilities Committee
On agenda: 2/7/2022 Final action: 2/10/2022
Title: To authorize the Director of Public Utilities to execute a planned modification to the 2020 - 2022 Construction Administration/ Inspection Services Agreement with EMH&T, Inc., for the Division of Sewerage and Drainage/Stormwater Section’s FRA-70/71 Phase 4R & 6R Project; to authorize a transfer and expenditure of up to $549,832.21 from the Storm Sewer Bond Fund; and to authorize an amendment the 2021 Capital Improvements Budget, and to declare an emergency. ($549,832.21)
Attachments: 1. Ord. 0294-2022 Utilization Reporting Form.pdf, 2. Ord. 0294-2022 Funding Template EMHT Mod 12.pdf
Explanation

1.0 BACKGROUND: This legislation authorizes the Director of Public Utilities to execute a planned modification to the 2020 - 2022 Construction Administration/Construction Inspection (CA/CI) Services agreement with Evans, Mechwart, Hambleton, and Tilton Inc. (“EMH&T”).

Funding for this modification will be for the following project:
· DOSD/Stormwater Section’s FRA-70/71 Phase 4R & 6R Project: $549,832.21

1.1. Amount of additional funds to be expended: $549,832.21
Original Agreement Amount: $521,938.79 PO216078 & PO216128
Modification 1 $340,200.00 PO222768 & PO222770
Modification 2 $265,476.00 PO231230
Modification 3 $144,797.71 PO232017
Modification 4 $638,637.08 PO241546
Modification 5 $1,220,302.58 PO254832, PO254835, PO254836, PO254837
Modification 6 $310,500.93 PO273172
Modification 7 $279,013.79 PO277870
Modification 8 $566,857.66 PO288541
Modification 9 $646,062.67 PO299464, PO299468
Modification 10 $1,052,396.86 PO308115, PO308136
Modification 11 $188,584.80 PO306158
Modification 12 (current) $549,832.21
Total (Orig. + Mods. 1-10) $6,724,601.08


1.2. Reasons additional goods/services could not be foreseen:
This is a three-year agreement for fiscal years 2020 - 2022 and modifications were anticipated and explained in the original legislation under Ordinance No. 0360-2020.

1.3. Reason other procurement processes are not used:
This is a multi-year contract that will be modified as required to provide construction administration/construction inspection services for construction projects that bid during the three year (2020-2022) time frame.

1.4. How cost of modification was determined:
The cost of this modification was determined by negotiations between EMH&T and the Division of Sewerage & Drainage/Stormwater Section.

2.0 ECONOMIC IMPACT/ADVANTAGES; COMMUNITY OUTREACH; PROJECT DEVELOPMENT; ENVIRONMENTAL FACTORS/ADVANTAGES OF PROJECT:
Division of Sewerage and Drainage projects include rehabilitation of e...