File #: 0355-2022    Version: 1
Type: Ordinance Status: Passed
File created: 1/27/2022 In control: Public Utilities Committee
On agenda: 2/28/2022 Final action: 3/2/2022
Title: To authorize the Director of Public Utilities to execute a planned modification of the 2020 - 2022 Construction Administration and Inspection Services Agreement with Resource International, Inc. for the Division of Water’s South Weyant Avenue Water Line Improvements Project; to authorize an expenditure of up to $462,066.68 within the Water General Obligation Bond Fund; and to amend the 2021 Capital Improvement Budget. ($462,066.68)
Attachments: 1. ORD 0355-2022 Information, 2. ORD 0355-2022 Utilization, 3. ORD 0355-2022 map, 4. ORD 0355-2022 Funding
Explanation

1.0 BACKGROUND:
This legislation authorizes the Director of Public Utilities to execute a planned modification to the 2020 - 2022 Construction Administration and Construction Inspection (CA/CI) Services agreement with Resource International, Inc.

Funding for this modification will be for the following project:

• Division of Water, South Weyant Avenue Water Line Improvements, CIP No. 690236-100097, CT No. 2121; Planning Area = 57 - Mid East; $462,066.68

1.1. Amount of additional funds to be expended: $462,066.68
Original Contract: $ 225,352.47 (PO222775)
Modification #1: $1,422,963.00 (PO228475, PO228476, PO228477, PO228478)
Modification #2: $ 169,985.96 (PO239948)
Modification #3: $ 862,887.72 (PO261079, PO261484, PO261488)
Modification #4: $1,023,884.71 (PO286992, PO286998, PO287003)
Modification #5: $ 744,529.85 (PO296089)
Modification #6: $ 951,081.48 (pending)
Modification #7: $ 564,947.72 (pending)
Modification #8 (current): $ 462,066.68
Total (Orig. + Mods 1-8) $6,427,699.74

1.2. Reasons additional goods/services could not be foreseen:
This is a three-year agreement for fiscal years 2020 - 2022 and modifications were anticipated and explained in the original legislation under Ordinance No. 0506-2020.

1.3. Reason other procurement processes are not used:
This is a multiyear contract that will be modified as required to provide construction administration/inspection services for construction projects that bid during the three year (2020-2022) timeframe.

1.4. How cost of modification was determined:
The cost of this modification was determined by negotiations between Resource International and the Division of Water.

2.0 ECONOMIC IMPACT/ADVANTAGES; COMMUNITY OUTREACH; PROJECT DEVELOPMENT; ENVIRONMENTAL FACTORS/ADVANTAGES OF PROJECT: Division of Water projects include replacement or rehabilitation of water lines that have a high break frequency and valves that are inoperable. Replacement of these water lines will i...