File #: 0533-2022    Version: 1
Type: Ordinance Status: Passed
File created: 2/15/2022 In control: Public Utilities Committee
On agenda: 3/21/2022 Final action: 3/23/2022
Title: To authorize the Director of Public Utilities to modify and increase the 2020 - 2022 Construction Administration and Inspection Services agreement with H. R. Gray & Associates, Inc. for the Division of Water’s Edsel Avenue Area Water Line Improvements Project; to authorize an expenditure up to $569,553.54 within the Water General Obligations Bond Fund; and to authorize an amendment to the 2021 Capital Improvements Budget. ($569,553.54)
Attachments: 1. ORD 0533-2022 Information, 2. ORD 0533-2022 Utilization, 3. ORD 0533-2022 map, 4. ORD 0533-2022 Funding
Explanation

1.0 BACKGROUND: This legislation authorizes the Director of Public Utilities to execute a planned modification to the 2020 - 2022 Construction Administration and Inspection Services agreement with H. R. Gray & Associates Inc. for the following Division of Water Project:

• Edsel Avenue Area Water Line Improvements, CIP No. 690236-100104, Contract No. 2128, Planning Area = 65 - Far South, $569,553.54

1.1. Amount of additional funds to be expended: $569,553.54
Original Agreement Amount: $ 167,845.34 PO228237, PO228238, & PO228239
Modification No. 1 $ 979,361.67 PO235282
Modification No. 2 $ 711,543.64 PO238195 & PO238199
Modification No. 3 $ 255,437.69 PO248167
Modification No. 4 $1,523,581.11 PO265076
Modification No. 5 $ 110,010.07 PO287159, PO287161
Modification No. 6 $ 864,726.79 PO296077, PO296083
Modification No. 7 $ 700,766.27 (pending)
Modification No. 8 $ 703,124.48 (pending)
Modification No. 9 (current) $ 569,553.54
Grand Total $6,585,950.60

1.2. Reasons additional goods/services could not be foreseen:
This is a three-year agreement for fiscal years 2020 - 2022 and modifications were anticipated and explained in the original legislation under Ordinance No. 0787-2020.

1.3. Reason other procurement processes are not used:
This is a multiyear contract that will be modified as required to provide construction administration/inspection services for construction projects that bid during the three year (2020-2022) timeframe.

1.4. How cost of modification was determined:
The cost was determined by negotiations between H.R. Gray & Associates and the Division of Water.

2.0 ECONOMIC IMPACT/ADVANTAGES; COMMUNITY OUTREACH; PROJECT DEVELOPMENT; ENVIRONMENTAL FACTORS/ADVANTAGES OF PROJECT: Division of Water projects include replacement or rehabilitation of water lines that have a high break frequency. Replacement of these water lines will improve water service, decrease burden on water maintenance operations, and reduce...