Title: To authorize the Director of Public Utilities to renew and increase the professional engineering services agreement with Hill International, Inc. for the Professional Construction Management Services - 2018 Project; for the Division of Water; to authorize a transfer and expenditure up to $3,931,400.00 within the Water General Obligations Bond Fund; and to amend the 2021 Capital Improvements Budget. ($3,931,400.00)
Attachments: 1. ORD 0975-2022 Information, 2. ORD 0975-2022 Utilization, 3. ORD 0975-2022 Funding
Explanation

1. BACKGROUND: This Ordinance authorizes the Director of Public Utilities to renew and increase the professional engineering services agreement with Hill International, Inc. for the Professional Construction Management Services (PCM) - 2018 Project.

The PCM assists the City with managing the capital improvement program consisting of multiple projects to ensure completion in accordance with design requirements and City’s needs, while serving as a liaison between the construction contractor, design professional (DP), and City personnel. The PCM team furnishes all necessary competent personnel, equipment, and materials to perform the work, which will generally consist of program support services, design phase services, and construction management services. Projects are assigned to this contract based on a two year assignment window. Funds are authorized through annual contract renewals (or more frequent renewals if required by fiscal needs).

Work performed to date includes program support services, design phase services, and construction management services. Future phases of the contact will continue program support services and construction management services.

This Renewal #5 will fund PCM services from June 2022 through May 2023.

Community planning is “99 - Citywide” because the water facilities associated with this contract serve multiple planning areas.

FUTURE RENEWALS: The PCM contract will provide construction services through completion of all assigned construction projects. The estimated contract end date is August 1, 2025, but the actual end date will depend on the construction duration of the 690278-100005, DRWP Misc. Imp's - Basin Clarifier Rehab project.

1.1 Amount of additional funds to be expended: $3,931,400.00
Original Contract Amount: $ 2,644,800.00
Renewal #1: $ 5,082,200.00
Modification #2: $ 5,603,300.00
Modification #3: $ 0.00 (time extension only)
Renewal #4: $ 5,429,700.00
Renewal #5 (cu...