File #: 2212-2022    Version: 1
Type: Ordinance Status: Passed
File created: 7/21/2022 In control: Public Utilities Committee
On agenda: 9/19/2022 Final action: 9/21/2022
Title: To authorize the Director of the Department of Public Utilities to modify and increase the 2020 - 2022 Construction Administration and Inspection Services agreement with H. R. Gray & Associates, Inc. for the Division of Sewerage & Drainage’s Roof Redirection - Blueprint North Linden 1, Agler/Berrell Project; and to authorize an expenditure up to $365,462.53 within the Sewer General Obligations Bond Fund. ($365,462.53)
Attachments: 1. ORD 2212-2022 Information, 2. ORD 2212-2022 Utilization, 3. ORD 2212-2022 map, 4. ORD 2212-2022 Funding
Explanation

1.0 BACKGROUND: This legislation authorizes the Director of the Department of Public Utilities to execute a planned modification to the 2020 - 2022 Construction Administration and Inspection Services agreement with H. R. Gray & Associates Inc. for the following Division of Sewerage & Drainage Project:

• Roof Redirection - Blueprint North Linden 1, Agler/Berrell, CIP No. 650871-141001, Planning Area = 40 - North Linden, $365,462.53

1.1. Amount of additional funds to be expended: $365,462.53
Original Agreement Amount: $ 167,845.34 PO228237, PO228238, & PO228239
Modification No. 1 $ 979,361.67 PO235282
Modification No. 2 $ 711,543.64 PO238195 & PO238199
Modification No. 3 $ 255,437.69 PO248167
Modification No. 4 $1,523,581.11 PO265076
Modification No. 5 $ 110,010.07 PO287159, PO287161
Modification No. 6 $ 864,726.79 PO296077, PO296083
Modification No. 7 $ 700,766.27 (PO314887, PO314895, PO314901)
Modification No. 8 $ 703,124.48 (PO322659)
Modification No. 9 $ 569,553.54 (PO330629)
Modification No. 10 $ 540,289.67 (PO330629)
Modification No. 11 (current) $ 365,462.53
Grand Total $7,491,702.80

1.2. Reasons additional goods/services could not be foreseen:
This is a three-year agreement for fiscal years 2020 - 2022 and modifications were anticipated and explained in the original legislation under Ordinance No. 0787-2020.

1.3. Reason other procurement processes are not used:
This is a multi-year contract that will be modified as ...