header-left
File #: 1046-2023    Version: 1
Type: Ordinance Status: Passed
File created: 3/29/2023 In control: Public Service & Transportation Committee
On agenda: 4/24/2023 Final action: 4/26/2023
Title: To amend the 2022 Capital Improvement Budget; to authorize the transfer of funds within the Streets and Highways Bond Fund; to authorize the Director of Public Service to enter into a contract modification with Arcadis US Inc., in connection with the Bridge Rehab - UIRF - Milo Grogan Second Avenue Improvements project; to authorize the expenditure of up to $35,000.00 from the Streets and Highways Bond Fund for the project; and to declare an emergency. ($35,000.00)
Attachments: 1. ORD 1046-2023 Accounting Templates.pdf
Explanation
1. BACKGROUND
This ordinance authorizes the Director of Public Service to modify a professional services contract with Arcadis US Inc., to add additional funds of $35,000.00 for design of the Bridge Rehab - UIRF - Milo Grogan Second Avenue Improvements.
Ordinance 0465-2017 authorized the Director of Public Service to enter into a professional services contract with Arcadis US Inc., for the Bridge Rehab - UIRF - Milo Grogan Second Avenue Improvements project. The contract is to produce construction plans and associated deliverables for improvements to East Second Avenue from Sixth Street to St. Clair Avenue. Improvements will generally consist of new pervious pavement in the parking lane of 2nd Avenue, resurfacing the remaining existing pavement, replacing the existing curb and installation of curb extensions to define the parking areas. Streetscape improvements will consist of replacement of existing sidewalks, new street trees, and new street lighting with underground circuit. The signals at Cleveland Avenue and St. Clair Avenue will be modified to accommodate the proposed improvements.

Ordinance 2933-2018 authorized the Director of Public Service to modify the contract due to expanding the scope of the project to include the City-owned retaining walls that are adjacent to the project area and assigning detailed design work.

Ordinance 3111-2021 authorized the Director of Public Service to modify the contract to include additional right of way, stormwater and utility design services.

Ordinance 1663-2022 authorized the Director of Public Service to modify the contract to include an additional residential wall design, geotech, and utility coordination.

This modification is necessary to cover the cost of reinforcing information to provide better information to the contractor to determine bid pricing and constructability. It was deemed to be more cost efficient to modify the existing contract than to bid this part of the work.

The original con...