File #: 1695-2023    Version: 1
Type: Ordinance Status: Passed
File created: 6/1/2023 In control: Housing Committee
On agenda: 7/17/2023 Final action: 7/21/2023
Title: To authorize the Director of the Department of Development to modify a contract with Charles D Jones dba C2U Construction LLC; to provide residential emergency repair services as part of the Division of Housing’s Emergency Repair Program; to authorize the transfer and expenditure of up to $15,000.00. ($15,000.00)
Indexes: MBE Participation
Attachments: 1. 1695-2023 Housing C2U Renewal GF 2023-06-05
Explanation

BACKGROUND
This legislation authorizes the Director of the Department of Development to modify a contract with Charles D Jones dba C2U Construction LLC to increase the contract amount by $15,000.00 to provide residential emergency repair services as part of the Division of Housing’s Emergency Repair Program.

Original contract amount $100,000.00 Ord. 0823-2023 PO380445
Modification No. 1 amount $ 75,000.00 Ord. 1520-2023
Modification No. 2 amount $ 15,000.00 Ord. 1695-2023
Total contract amount $190,000.00

The department advertised and notified 401 registered vendor of RFQ022527 on August 2, 2022, and 626
registered vendors were notified of RFQ023115 on October 11, 2022, through Vendor Services seeking
contractors to provide emergency electrical services. Both competitively bid processes did not receive
bids from contractors. The Department of Development then sent eight (8) targeted emails to contractors
requesting firm/fixed pricing to be submitted by December 16, 2022 from vendors that responded through
outreach events.

Two (2) contractors replied with pricing, Charles D. Jones dba C2U Construction LLC (registered with
the city, but not certified MWBE firm) and Word of Mouth Electric & Rehab LLC (registered with the
city, but not certified MWBE firm). Only Charles D. Jones dba C2U Construction LLC provided
firm/fixed pricing. C2U Construction LLC shall have one subcontractor, McGhee Electric LLC (not
registered with the City).

The amount of additional funds expended under this modification will be $15,000.00. The need for additional goods/services could not be foreseen at the time the contract was initially awarded due to an updated interpretation of the allowable scope of work for capital funds, that resulted in a need for general fund dollars for home repair project scopes that do not fit the requirements for capital funds.

A comprehensive RFQ was done in 2021 for these services, and contractors were identified at that time. A new RFQ...

Click here for full text