File #: 1713-2023    Version: 1
Type: Ordinance Status: Passed
File created: 6/2/2023 In control: Public Utilities Committee
On agenda: 7/17/2023 Final action: 7/21/2023
Title: To authorize a revision of the scope of the Jackson Pike Screening Improvements project to meet immediate needs so that the current facility can remain operational until a new facility can be designed and constructed. ($0.00)
Indexes: WBE Participation
Attachments: 1. ORD 1713-2023 Utilization
Explanation
1. BACKGROUND
This ordinance authorizes the Director of Public Utilities to enter into a contract modification with Burgess & Niple, Inc. for professional services and construction services for the JP Screening Improvements (Engineering Mod #2) project, CIP #650252-100010.

This is a contract with Burgess & Niple for Professional Engineering Services (Design Professional, or “DP” services) for the JPWWTP Screenings Improvements project. Burgess & Niple has provided Preliminary Design Services (Step 1) and will provide Detailed Design and Bidding Services (Step 2) and Services During Construction (Step 3).

During Step 2, Detailed Design, the City determined that a new screenings facility with the proper space, redundancy, and equipment is needed to meet current wastewater standards. The new facility will be designed and constructed in the near future when budget allows. As a result of this decision, this unplanned modification is being generated to revise and reduce the scope of this project to meet immediate needs so that the current facility can remain operational until the project that includes the new facility can be designed and constructed.

A future, third modification will be requested for Step 3, Engineering Services During Construction, which will include technical project representation (TPR) duties, construction phase engineering, start-up and commissioning assistance, and record documentation.

Construction Management Services will be performed by others.

Planning Area is Citywide
The Community Planning Area is “99 - Citywide”.
TIMELINE: The Professional Engineer Services Agreement was signed in May 2019 and provided Step 1, Preliminary Design Services. Step 2 services began in May of 2021 and are anticipated to end in the first quarter of 2024. Construction Bids are anticipated to be received in the second quarter of 2024 and it is anticipated that the Notice to Proceed for the construction contract will be given in the thi...

Click here for full text