File #: 2190-2023    Version: 1
Type: Ordinance Status: Passed
File created: 7/13/2023 In control: Public Utilities Committee
On agenda: 9/18/2023 Final action: 9/21/2023
Title: To authorize the Director of Public Utilities to enter into a construction contract with Fields Excavating for the Atwood Terrace Area Water Line Improvements project; to authorize an amendment to the 2023 Capital Improvement Budget; to authorize the appropriation and transfer of funds from the Water System Reserve Fund to the Water Supply Revolving Loan Account Fund; to authorize the appropriation and expenditure of an amount not to exceed $5,193,787.50 from the Water Supply Revolving Loan Account Fund for the contract; to authorize the transfer of cash and appropriation between projects within the Water Bond Fund; and to authorize the expenditure of an amount not to exceed $2,000.00 from the Water Bond Fund to pay for construction administration and inspection expenses for the project. ($5,195,787.50)
Indexes: EBE Participation, MBE Participation
Attachments: 1. ORD 2190-2023 Accounting Template, 2. ORD 2190-2023 Utilization

Explanation   

1.  BACKGROUND

This ordinance authorizes the Director of Public Utilities to enter into a construction contract with Fields Excavating, Inc., for the Atwood Terrace Area Water Line Improvements, CIP #690236-100099, in an amount not to exceed  $5,193,787.50, and to encumber funds with the Department of Public Service for construction administration and inspection services in an amount not to exceed $2,000.00, for a total expenditure of $5,195,787.50. 

 

Work consists of the installation of approximately 11,500 lineal feet of 6-inch and 8-inch water mains, water tap transfers, fire hydrant installations, and other such work as may be necessary to complete the contract, in accordance with the drawings, technical specifications, special provisions, and City of Columbus Construction and Material specifications.

 

The Community Planning Area is 40 - North Linden.

 

TIMELINE:  All work shall be complete within 365 calendar days from the Notice to Proceed.  The City anticipates issuing a Notice to Proceed on or about November, 2023.

ESTIMATED COST OF PROJECT: The bid amount and proposed award amount is $5,193,787.50, including a 10% construction contingency amount that will be utilized to fund needed and approved changes in the work.  No contract modifications are anticipated at this time; however, construction exigency might later compel modification of this contract, if unforeseen difficulties are encountered.

 Cost summary:

             Original Contract                                                                                 $5,193,787.50                                         

                     Future Anticipated Needs                                                            $             0.00

                     CONTRACT TOTAL                                                                                 $5,193,787.50

                     DPS Davis Bacon Wage Rate Administration                                            $       2,000.00

             TOTAL LEGISLATION                                                                              $5,195,787.50

 

2.  ECONOMIC IMPACT/ADVANTAGES; COMMUNITY OUTREACH; PROJECT DEVELOPMENT; ENVIRONMENTAL FACTORS/ADVANTAGES OF PROJECT

The goal of this project is to replace existing water lines that have a high break frequency.  Replacement of these water lines will improve water service, decrease burden on water maintenance operations, and reduce water loss.  The Neighborhood Liaison(s) has been contacted and informed of this project during the design phase.  Further community outreach may result through the Neighborhood Liaison Program.

 

3.  CONSTRUCTION CONTRACT AWARD

An Invitation for Bids for the Atwood Terrace Area Water Line Improvements project was advertised on the Vendor Services and Bid Express websites from 5/24/23 through 6/21/23.  Three bids were received for the project and were opened on 6/21/23.  The following companies submitted bids:

 

Company                                                                  Bid Amount                        Compliance Number       ODI Status

Fields Excavating, Inc.                                    $5,193,787.50                                   CC-005416                                          MAJ

Danbert, Inc.                                                                 $5,200,017.55                                              CC-004618                                          MAJ

Elite Excavating Co. of Ohio, Inc.   $5,809,766.60                        CC-004618                                          MAJ

 

The Fields Excavating, Inc., bid was deemed the lowest, best, most responsive and responsible bid in the amount of $5,193,787.50. 

 

The certification of Fields Excavating, Inc. was in good standing at the time the bid was awarded.

 

4.  CONTRACT COMPLIANCE INFORMATION

Fields Excavating, Inc.'s contract compliance number is CC-005416 and expires 7/14/24.  

 

Searches in the Excluded Party List System (Federal) and the Findings for Recovery list (State) produced no findings against Fields Excavating, Inc.

 

5.  MINORITY AND WOMAN OWNED BUSINESS ENTERPRISE & SMALL LOCAL BUSINESS ENTERPRISE PROGRAM

This contract was bid with an anticipated City of Columbus MBE/WBE Program goal of 15% as assigned by the City’s Office of Diversity and Inclusion (ODI).  After ODI’s review of the Utilization Plan and other related information the contractor submitted with their bid response, ODI has approved an MBE/WBE Program goal of 15% for this contract.  The contractor will not be contractually liable for achieving an MBE/WBE goal. 

 

As part of their proposal, Fields Excavating, Inc. has proposed the following subcontractor to perform contract work:

 

Company Name                                            City/State                                     ODI Certification Status

Donley Concrete Cutting                                        Columbus, Ohio                                                                                    MAJ

Strawser Paving Co.                                     Columbus, Ohio                                                                                     MAJ

Griffin Pavement Striping                                        Columbus, Ohio                                                                             MAJ

Contractor Connection Inc                                        Canton, Ohio                                                                                    MBE

Rath Builders Supply Inc                                                 Defiance, Ohio                                                                                     EBE

K. Davis Inc.                                                                         Gibsonburg, Ohio                                                                                     EBE

 

The certification of all subcontractors was in good standing at the time the bid was awarded.

 

6.  PRE-QUALIFICATION STATUS

Fields Excavating, Inc. and all subcontractors have met code requirements with respect to pre-qualification, pursuant to relevant sections of Columbus City Code Chapter 329. 

 

7.  FISCAL IMPACT

The construction portion of this project is anticipated to be financed with a loan from the Water Supply Revolving Loan Account (WSRLA).  This loan program is jointly administered by the Ohio EPA’s Division of Environmental and Financial Assistance (DEFA) and the Ohio Water Development Authority (OWDA).  City Council authorized this loan application and acceptance of funding via Ordinance 1107-2022, passed by Council on 5/9/22.  This loan is anticipated to be approved in August of 2023.

 

A transfer of funds from the Water System Reserve Fund, Fund 6003, to the Water Supply Revolving Loan Account Fund, Fund 6011, in the amount of $5,193,787.50 is needed to fund construction for this project.  This transaction is a temporary measure that is required until a loan is executed with the Ohio EPA to reimburse the Water System Reserve Fund.  These funds will also need to be appropriated to be transferred and then appropriated after transfer to the new fund.  An amendment to the 2023 Capital Improvement Budget is needed to align budget authority with the proper project. 

 

The construction administration amount of $2,000.00 is available in the Water Bond Fund, Fund 6006.  A transfer of cash and appropriation between projects within the Water Bond Fund is needed to align cash and appropriation with the proper project.

 

Title

To authorize the Director of Public Utilities to enter into a construction contract with Fields Excavating for the Atwood Terrace Area Water Line Improvements project; to authorize an amendment to the 2023 Capital Improvement Budget; to authorize the appropriation and transfer of funds from the Water System Reserve Fund to the Water Supply Revolving Loan Account Fund; to authorize the appropriation and expenditure of an amount not to exceed $5,193,787.50 from the Water Supply Revolving Loan Account Fund for the contract; to authorize the transfer of cash and appropriation between projects within the Water Bond Fund; and to authorize the expenditure of an amount not to exceed $2,000.00 from the Water Bond Fund to pay for construction administration and inspection expenses for the project.  ($5,195,787.50)

 

Body

WHEREAS, the Department of Public Utilities is engaged in the Atwood Terrace Area Water Line Improvements project ("Project"); and

 

WHEREAS, three bids for the Atwood Terrace Area Water Line Improvements project were received and opened on 6/21/23; and

 

WHEREAS, the lowest, best, most responsive and responsible bid was from Fields Excavating, Inc.; and

 

WHEREAS, it is necessary to authorize the Director of the Department of Public Utilities to enter into a construction contract with Fields Excavating, Inc., for the Atwood Terrace Area Water Line Improvements project; and

 

WHEREAS, Ordinance No. 1107-2022 authorized this project to be funded by a loan to be obtained through the Water Supply Revolving Loan Account (WSRLA) Loan; and

 

WHEREAS, the 2023 Capital Improvement Budget must be modified to align budget authority with the proper project; and

 

WHEREAS, it is necessary to both appropriate and transfer funds from the Water System Reserve Fund to the Water Supply Revolving Loan Account; and

 

WHEREAS, the City anticipates incurring certain Original Expenditures (as defined in Section 1.150-2(c) of the Treasury Regulations (the “Treasury Regulations” promulgated pursuant to the Internal Revenue Code of 1986, as amended)) with respect to the construction of the Project described in this Ordinance; and

 

WHEREAS, it is necessary to appropriate and expend funds from the Water Supply Revolving Loan Account Fund to pay for the construction of this Project; and

 

WHEREAS, it is necessary to transfer cash and appropriation between projects in the Water Bond Fund, Fund 6006, to align cash and appropriation with the proper project; and

 

WHEREAS, it is necessary to expend funds from the Water Bond Fund to pay the Department of Public Service for construction administration and inspection services for this Project; now, therefore

 

BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:

 

SECTION 1.  That the 2023 Capital Improvement Budget authorized by Ordinance 1711-2023 be amended as follows to establish sufficient budget authority for this project:

 

Fund / Project Number / Project Name (Funding Source) / Current Authority/ Revised Authority / Change

6011 / 690236-100099 / Atwood Terrace Area Water Line Improvements (WSRLA Loan) / $3,500,000.00 / $5,193,788.00 / $1,693,788.00 (To match the loan amount)

6006 / 690236-100085 / Livingston Avenue Area 12" WL Imp's / $46,621.00 / $44,621.00 / ($2,000.00)

6006 / 690236-100099 / Atwood Terrace Area Water Line Improvements / $0.00 / $2,000.00 / $2,000.00

 

SECTION 2.  That from the unappropriated monies and from all monies estimated to come into said fund from any and all sources, and unappropriated for any other purpose during the fiscal year ending December 31, 2023, the sum of $5,193,787.50 is appropriated in the Water System Reserve Fund, Fund 6003, per the account codes in the funding attachment to this ordinance.

 

SECTION 3.  That the transfer of $5,193,787.50 or so much thereof as may be needed, is hereby authorized between the Water System Reserve Fund, Fund 6003, and the Water Supply Revolving Loan Account Fund, Fund 6011, per the accounting codes in the attachment to this ordinance.

 

SECTION 4.  That from the unappropriated monies and from all monies estimated to come into said fund from any and all sources, and unappropriated for any other purpose during the fiscal year ending December 31, 2023, the sum of $5,193,787.50 is appropriated in the Water Supply Revolving Loan Account Fund, Fund 6011, per the account codes in the funding attachment to this ordinance.

 

SECTION 5.  That the transfer of $2,000.00, or so much as may be needed, is hereby authorized between projects in the Water Bond Fund, Fund 6006, per the account codes in the funding attachment to this ordinance.

 

SECTION 6.  That the Director of Public Utilities is hereby authorized to enter into a construction contract for the Atwood Terrace Area Water Line Improvements project with Fields Excavating, Inc., 177 Twp. Rd 191, Kitts Hill, OH 45645, in an amount not to exceed $5,193,787.50; in accordance with the terms and conditions of the contract on file in the Department of Public Utilities; and to obtain the necessary construction administration and inspection services for this project from the Department of Public Services in an amount not to exceed $2,000.00.

 

SECTION 7.  That the expenditure of $5,195,787.50, or so much thereof as may be needed, is hereby authorized to pay for this contract per the accounting codes in the attachment to this ordinance.

 

SECTION 8.  That upon obtaining other funds for the purpose of funding water system capital improvement work, the City Auditor is hereby authorized to repay the Water System Reserve Fund the amount transferred above (Section 3), and said funds are hereby deemed appropriated for such purposes.

 

SECTION 9.  That the City intends that this Ordinance constitute an "official intent" for purposes of Section 1.150-2(e) of the Treasury Regulations, and that the City reasonably expects to reimburse itself for certain Original Expenditures incurred with respect to the Project from the proceeds of obligations to be issued by the City in a principal amount currently estimated to be $5,193,787.50 (the "Obligations").

 

The City intends to make a reimbursement allocation on its books for the Original Expenditures not later than eighteen months following the later to occur of the date of the Original Expenditure to be reimbursed or the date the Project for which such Original Expenditures were made is "placed in service" within the meaning of Treasury Regulations Section 1.150-2(c).  Upon the issuance of the Obligations, the proceeds of such Obligations shall be used to reimburse Water System Reserve Fund, Fund 6003, which is the fund from which the advance for costs of the Project will be made.

 

SECTION 10.  Funds are hereby deemed appropriated and expenditures and transfers authorized to carry out the purposes of this ordinance and the City Auditor shall establish such accounting codes as necessary.

 

SECTION 11.  That the City Auditor is authorized to make any accounting changes to revise the funding source for all contracts or contract modifications associated with this ordinance.

 

SECTION 12.  That the City Auditor is hereby authorized to transfer the unencumbered balance in a project account to the unallocated balance account within the same fund upon receipt of certification by the Director of the Department administering said project that the project has been completed and the monies are no longer required for said project.

 

SECTION 13.  That this ordinance shall take effect and be in force from and after the earliest period allowed by law.