-----Original
Message-----
From: Westerfield,
Richard C
Sent: Monday, April
27, 2009 2:43 PM
To: Hubbard,
Jeffrey A.
Cc: Arsh, Tanya;
Aubry, Ann M.
Subject: RE:
Fulton St Revised Contract Proposal
Please proceed. I understand that they need to proceed by 3:30 pm today.
-----Original Message-----
From: Hubbard, Jeffrey A.
Sent: Monday, April 27, 2009 9:12 AM
To: Westerfield, Richard C
Subject: FW: Fulton St Revised Contract ProposalI understand that we will have to do a Mod for this….but since the County is reimbursing us do you think we can proceed once the Co approves it ?
-----Original Message-----
From: Nate McCune [mailto:nmccune@completegeneral.com]
Sent: Friday, April 24, 2009 3:56 PM
To: Schneider, Robert R
Cc: gbrown@completegeneral.com; mlynch@completegeneral.com; 'Mark Young'; khood@pizzuti.com; Tomblin, David N.; Pittman, Gary; Hubbard, Jeffrey A.
Subject: Fulton St Revised Contract Proposal
Dear Sir,
Attached is Complete General Const. proposed cost to perform open trench instead of directional boring on Fulton St. 15kv Relocation.
Please review and respond at your earliest convenience. CGC will continue this operation once we receive approval. CGC will forward revised schedule at that time too.
Respectfully,
Nathan B. McCune
Project Manager
Complete General Const. Co
office 614-384-2339
fax 614-251-2900