Title: To authorize the Director of the Department of Public Utilities to enter into a construction contract with K & W Roofing, Inc. for the Jackson Pike Waste Water Treatment Plant DC3 and DC4 Roof Replacement project; to authorize an amendment to the 2023 Capital Improvement Budget; and to authorize the expenditure of up to $414,680.00 for the project. ($414,680.00)
Indexes: WBE Participation
Attachments: 1. ORD 0683-2024 Utilization, 2. ORD 0683-2024 Accounting Template
Explanation
1. BACKGROUND
This ordinance authorizes the Director of Public Utilities to enter into a construction contract with K & W Roofing, Inc. for the Jackson Pike WWTP DC3 and DC4 Roof Replacement project, CIP #650234-100111, in an amount up to $412,680.00, and to encumber funds with the Department of Public Service for prevailing wage services in an amount up to $2,000.00, for a total expenditure of $414,680.00.

This is a contract for the complete roof replacement of the Jackson Pipe WWTP West DC3 and DC4. The work consists of roof removal to the deck, partial roof deck repair, new roof system installation, reinstallation of lightning protection systems, and other such work as may be necessary to ensure that the building is watertight.

The Community Planning Area is 59 - Southwest.

TIMELINE: Contract work is required to be completed in a manner acceptable to the City within 230 days from the date that a Notice to Proceed (NTP) is given by the City.

ESTIMATED COST OF PROJECT: The bid amount and proposed award amount is $412,680.00, including a 20% construction contingency amount that will be utilized to fund needed and approved changes in the work. No contract modifications are anticipated at this time; however, construction exigency might later compel modification of this contract, if unforeseen difficulties are encountered.

Cost summary:

Original Contract $412,680.00
Future Anticipated Needs $ 0.00
CONTRACT TOTAL $412,680.00
Prevailing Wage Charge $ 2,000.00
$414,680.00

2. ECONOMIC IMPACT/ADVANTAGES; COMMUNITY OUTREACH; PROJECT DEVELOPMENT; ENVIRONMENTAL FACTORS/ADVANTAGES OF PROJECT
Roof replacement of a failed roofing system provides watertight environmental controls to the important process equipment and building components housed in the structure. Removal and replacement of the failed equipment, electronic and electrical components, would be a major impact to the budget. No community outreach ...