File #: 0701-2024    Version: 1
Type: Ordinance Status: Passed
File created: 3/1/2024 In control: Public Utilities & Sustainability Committee
On agenda: 4/15/2024 Final action: 4/19/2024
Title: To authorize the Director of the Department of Public Utilities to enter into a construction contract with General Maintenance and Engineering Co., for the Southerly Waste Water Treatment Plant West Primary Control Roof Replacement project; to authorize an amendment to the 2023 Capital Improvement Budget; to authorize the appropriation and transfer of funds from the Sanitary Reserve Fund to the Sanitary-Fresh Water Market Rate Program Fund; to authorize the appropriation and expenditure of up to $216,000.00 from the Sanitary-Fresh Water Market Rate Program Fund for the contract; and to authorize an expenditure of up to $2,000.00 from the Sanitary Bond Fund to pay for the prevailing wage services for the project. ($218,000.00)
Indexes: MBE Participation
Attachments: 1. ORD 0701-2024 Utilization, 2. ORD 0701-2024 Accounting Template
Explanation
1. BACKGROUND
This ordinance authorizes the Director of Public Utilities to enter into a construction contract with General Maintenance and Engineering Co. for the Southerly Waste Water Treatment Plant (SWWTP) West Primary Control (WPC) Roof Replacement project, CIP #650234-100113, in an amount up to $216,000.00, and to encumber funds with the Department of Public Service for prevailing wage services in an amount up to $2,000.00, for a total expenditure of $218,000.00.

This is a contract for the complete roof replacement of the Southerly WWTP West Primary Control Building Roof. The work consists of roof removal to the deck, partial roof deck repair, new roof system installation, reinstallation of lightning protection systems, and other such work as may be necessary to ensure that the building is watertight.

Planning Area - 64 - Far South.

TIMELINE: Contract work is required to be completed in a manner acceptable to the City within 180 days from the date that a Notice to Proceed (NTP) is given by the City.

ESTIMATED COST OF PROJECT: The bid amount and proposed award amount is $216,000.00, including a 20% construction contingency amount that will be utilized to fund needed and approved changes in the work. No contract modifications are anticipated at this time; however, construction exigency might later compel modification of this contract, if unforeseen difficulties are encountered.

Cost summary:

Original Contract $216,000.00
Future Anticipated Needs $ 0.00
CONTRACT TOTAL $216,000.00
Prevailing Wage Charge $ 2,000.00
$218,000.00

2. ECONOMIC IMPACT/ADVANTAGES; COMMUNITY OUTREACH; PROJECT DEVELOPMENT; ENVIRONMENTAL FACTORS/ADVANTAGES OF PROJECT
Roof replacement of a failed roofing system p...

Click here for full text