Explanation
1. BACKGROUND
This legislation authorizes the Director of Public Service to modify a design contract with ms consultants, inc. for the Arterial Street Rehabilitation - Hamilton Road - I-70 to Refugee Road project.
This project, also known as FRA-SR317-10.630 (PID Number 95570), includes the completion of the Project Development Process (PDP) for improvements to S. Hamilton Road from approximately 1500’ south of Refugee Road to approximately 550’ north of Groves Road and Refugee Road from approximately 500’ west of S. Hamilton Road to approximately 1900’ east of S. Hamilton Road. The primary purpose of the project is to upgrade the roadway, sidewalk, bikeway facilities and aesthetic elements within the City of Columbus right-of-way along Hamilton Road in the Eastland Area, also known as Community Planning Area 24.
This planned modification provides funding for the continuation of previously approved work.
Original amount of this contract $250,000.00 (Ord. 2793-2013; EL015562)
Modification number 1 $474,943.66
The total amount of the contract, including this modification is $724,943.66.
Searches in the System for Award Management (Federal) and the Findings for Recovery list (State) produced no findings against ms consultants, inc.
2. CONTRACT COMPLIANCE
The contract compliance number for ms consultants, inc. is 34-6546916 and expires 3/7/16.
3. FISCAL IMPACT
Funds in the amount of $474,943.66 are available for this project in the Streets and Highways Bond Fund within the Department of Public Service. This ordinance is contingent upon receipt of bond sale proceeds.
4. EMERGENCY DESIGNATION
Emergency action is requested to provide necessary engineering and design funding and prevent unnecessary delays in the Department of Public Service’s Capital Improvement Program.
Title
To authorize the Director of Public Service to modify an existing design contract with ms consultants, inc. for the Arterial Street Rehabilitation - Hamilton Road...
Click here for full text