File #: 1608-2018    Version: 1
Type: Ordinance Status: Passed
File created: 6/4/2018 In control: Public Utilities Committee
On agenda: 7/9/2018 Final action: 7/12/2018
Title: To authorize the Director of Public Utilities to enter into a construction contract with CB&I Constructors LLC for the Westgate East 2 MMG Elevated Storage Tank Project; to authorize a transfer and expenditure up to $5,331,500.00 within the Water General Obligation Voted Bonds Fund; to provide for payment of prevailing wage services to the Department of Public Service, Design and Construction Division for the Division of Water; and to authorize an amendment of the 2018 Capital Improvements Budget. ($5,331,500.00)
Attachments: 1. ORD 1608-2018 Bid Tab, 2. ORD 1608-2018 QFF, 3. ORD 1608-2018 Information, 4. ORD 1608-2018 Utilization, 5. ORD 1608-2018 map, 6. ORD 1608-2018 Funding
Explanation

1. BACKGROUND: This legislation authorizes the Director of Public Utilities to enter into a construction contract with CB&I Constructors LLC for the Westgate East 2 MMG Elevated Storage Tank Project; in an amount up to $5,329,500.00; and to encumber funds with the Department of Public Service, Design and Construction Division for prevailing wage services in the amount of $2,000.00, for Division of Water Capital Improvements Project No. 690537-100001, Contract No. 2032.

This project will provide for the construction of a new 2 MMG elevated water storage tank to serve the Mound Pressure District. Site work includes: storm and sanitary sewer, grading, paving, and other such work as may be necessary to complete the contract in accordance with the plans and technical specifications.

Community planning area: “Hilltop”

2. ECONOMIC IMPACT/ADVANTAGES; COMMUNITY OUTREACH; PROJECT DEVELOPMENT; ENVIRONMENTAL FACTORS/ADVANTAGES OF PROJECT:
This tank will replace a previously demolished tank that had exceeded its useful life and was no longer serviceable. This replacement tank will provide redundancy for water storage and reliable water pressure in the Mound Pressure District. Community outreach has included coordination with the Hilltop Area Commission and the Friend of Westgate Park organization.

3.0 CONSTRUCTION CONTRACT AWARD: The Director of Public Utilities publicly opened three bids on May 16, 2018 from:

1. CB&I Constructors $5,329,500.00
2. Caldwell Tanks $5,688,100.00 (after bid tab correction)
3. Landmark Structures $5,875,100.00

3.1 PRE-QUALIFICATION STATUS: CB&I Constructors LLC and all proposed subcontractors have met code requirements with respect to pre-qualification, pursuant to relevant sections of Columbus City Code Chapter 329.

CB&I Constructors’s bid was deemed the lowest, ...