File #: 0014-2016    Version: 1
Type: Ordinance Status: Passed
File created: 12/17/2015 In control: Public Utilities Committee
On agenda: 2/1/2016 Final action: 2/5/2016
Title: To authorize the Director of Public Utilities to execute a construction contract with Burch Hydro, Inc. for the Hap Cremean Water Plant (HCWP) Lagoon No. 1 Sludge Removal - 2015 Project in the amount of $1,584,206.66; to authorize a transfer and expenditure up to $1,584,206.66 within the Water GO Bond Fund for the Division of Water; and to authorize an amendment to the 2015 Capital Improvements Budget. ($1,584,206.66)
Attachments: 1. ORD 0014-2016 Bid tab, 2. ORD 0014-2016 QFF, 3. ORD 0014-2016 Information, 4. ORD 0014-2016 Amend CIB, 5. ORD 0014-2016 Funding, 6. ORD 0014-2016 SWIF, 7. ORD 0014-2016 map
Explanation

1. BACKGROUND: This legislation authorizes the Director of Public Utilities to enter into a construction contract with Burch Hydro, Inc. in an amount up to $1,584,206.66 for the Hap Cremean Water Plant (HCWP) Lagoon No. 1 Sludge Removal - 2015 Project, Division of Water Contract Number 2108.

This project consists of removing sludge from Lagoon No. 1 and potentially a portion of the sludge in Lagoon No. 2 at the HCWP.

The planning area for this project “Citywide” since the HCWP provides water to several communities.

2. ECONOMIC IMPACT/ADVANTAGES; COMMUNITY OUTREACH; PROJECT DEVELOPMENT; ENVIRONMENTAL FACTORS/ADVANTAGES OF PROJECT: The removal of sludge from Lagoon No. 1 will provide additional storage for emergency situations due to loss of pumping capabilities and for maintenance shutdown of the pumping equipment. Additional storage space will allow decantation of the sludge and significantly increase the useful life of the lagoon. This work is being performed at a secure facility and no public outreach was performed as part of this project.

3.0 CONSTRUCTION CONTRACT AWARD: The Director of Public Utilities publicly opened one bid on December 9, 2015 from Burch Hydro, Inc. in the amount of $1,584,206.66.

3.1 PRE-QUALIFICATION STATUS: Burch Hydro, Inc. and all proposed subcontractors have met code requirements with respect to pre-qualification, pursuant to relevant sections of Columbus City Code Chapter 329.

Burch Hydro’s bid was deemed the lowest, best, most responsive and responsible bid in the amount of $1,584,206.66. Their Contract Compliance Number is 31-0978934 (expires 9/2/17, Majority). Additional information regarding this bidder, description of work, contract time frame and detailed amount can be found on the attached Information form.

Searches in the Excluded Party List System (Federal) and the Findings for Recovery list (State) produced no findings against Burch Hydro, Inc.

4. FISCAL IMPACT: A transfer of funds wit...