File #: 1169-2015    Version: 1
Type: Ordinance Status: Passed
File created: 4/22/2015 In control: Public Service & Transportation Committee
On agenda: 5/11/2015 Final action: 5/13/2015
Title: To amend the 2015 Capital Improvement Budget; to authorize the City Auditor to transfer cash and appropriation within the Street and Highway G.O. Bond Fund; to authorize the Director of Public Service to enter into contract with G&G Cement Contractors, and to provide for the payment of construction administration and inspection services in connection with the ADA Curb Ramps - Citywide Curb Ramps 2014 project; to authorize the expenditure of up to $686,176.21 from the Streets and Highways Bonds Fund; and to declare an emergency. ($686,176.21)

Explanation
1. BACKGROUND:
This legislation authorizes the Director of Public Service to enter into a contract for the construction of the ADA Curb Ramps - Citywide Curb Ramps 2014 project and to provide payment for construction administration and inspection services.

The ADA Curb Ramps - Citywide Curb Ramps 2014 project consists of building ADA curb ramps at various locations in the City of Columbus. These are high priority ramps based on 311 Service Requests received.

The estimated Notice to Proceed date is May 27, 2015. The Office of Support Services let the project through Vendor Services and Bid Express. Five bids were received on April 7, 2015, (five majority) and tabulated as follows:

Company Name Bid Amt City/State Majority/MBE/FBE
G&G Cement Contractors 596,674.21 Columbus, OH Majority
Decker Construction Company 707,303.39 Columbus, OH Majority
Strawser Paving Company Inc. 751,401.63 Columbus, OH Majority
Columbus Asphalt Paving Inc. 777,690.85 Gahanna, OH Majority
Shelly and Sands, Inc. 911,983.60 Columbus, OH Majority

G&G Cement Contractors will receive the award as they are the lowest, responsive, responsible and best bidder. The contract amount will be $596,674.21. The inspection amount will be $89,502.00. The total legislated amount is $686,176.21.

Searches in the System for Award Management (Federal) and the Findings for Recovery list (State) produced no findings against G&G Cement Contractors.

Pre-Qualification Status
G&G Cement Contractors and all proposed subcontractors have met code requirements with respect to pre-qualification, pursuant to relevant sections of Columbus City Code Chapter 329.

2. CONTRACT COMPLIANCE
The contract compliance number for G&G Cement Contractors is 310924129 and expires 06/23/16.

3. FISCAL IMPACT
The 2015 Capital Improvements Budget includes funding f...