header-left
File #: 0425-2018    Version: 1
Type: Ordinance Status: Passed
File created: 1/31/2018 In control: Finance Committee
On agenda: 3/12/2018 Final action: 3/14/2018
Title: To authorize the Director of Finance and Management to enter into a contract on behalf of the Office of Construction Management with Bomar Construction Company for relocation of the City Treasurer Cashier/Tellers Office; and to authorize the expenditure of $47,619.00 from the Construction Management Capital Improvement Fund. ($47,619.00)
Attachments: 1. 0425-2018
Explanation

BACKGROUND: This legislation authorizes the Finance and Management Director to enter into a contract on behalf of the Office of Construction Management with Bomar Construction Company for relocation of the City Treasurer Cashier/Tellers Office.
This legislation authorizes a contract for relocation of the City Treasurer Cashier/Tellers Office to the previous Sinking Fund Office, located on the first floor in City Hall. This relocation will improve office space efficiency in City Hall by better aligning the space needs of City Treasurer staff and visiting customers. The project will also allow for the restoration of the west entrance to make it consistent with the original layout of City Hall. This project will include, but is not limited to, flooring, countertops, door hardware, and wireless Matrix security system improvements.
Formal bids were solicited and the city received two bids on January 10, 2018 as follows (1 *FBE, 0 MBE):
*Bomar Construction Company $47,619.00
R.W. Setterlin Building Company $61,425.00

The Office of Construction Management recommends the bid be made to the most responsive and responsible bidder, Bomar Construction Company.
Bomar Construction Company Contract Compliance No. 31-1430310, expiration date November 30, 2020.
Fiscal Impact: This legislation authorizes the expenditure of $47,619.00 from the Construction Management Capital Improvement Fund with Bomar Construction Company for relocation of the City Treasurer Cashier/Tellers Office. The Finance Department budgeted $50,000.00 for this project within the Finance and Management capital budget.
Title

To authorize the Director of Finance and Management to enter into a contract on behalf of the Office of Construction Management with Bomar Construction Company for relocation of the City Treasurer Cashier/Tellers Office; and to authorize the expenditure of $47,619.00 from the Construction Management Capital Improvement Fund. ($47,619.00)