Explanation
1. BACKGROUND
This legislation authorizes the Director of Public Service to modify and increase an existing contract with Complete General Construction for the Glick Road Bridge Repairs project in an amount up to $80,000.00.
Ordinance 1054-2017 authorized the Director of Public Service to enter into a contract with Complete General Construction for the construction of the Glick Road Bridge Repairs project and to provide for construction administration and inspection services.
The work performed to date for this project consists of concrete bridge deck overlay and expansion joint improvements.
During the course of performing the repairs the contractor found additional damage that needs to be repaired (cracking at the bridge deck joints). It was also discovered a core item needed for the repair (repairing strip seals on the deck surface) was left off of the original bid list. The work for modification 1 will consist of performing these repairs, and other such work as may be necessary to complete the contract.
The original contract amount, no inspection: $510,249.25 (PO061314, Ord. 1054-2017)
The total of Modification No. 1, no inspection: $80,000.00 (This Ordinance)
The contract amount including all modifications: $590,249.25
Searches in the System for Award Management (Federal) and the Findings for Recovery list (State) produced no findings against Complete General Construction.
2. UNPLANNED MODIFICATION/BIDDING WAIVER REQUEST
This is an unplanned modification that is necessary to cover the cost of an item needed for the project that was not included in the bidding process. This work exceeded the project’s contingency amount. Tasks to be paid as part of the modification include repairing cracking at bridge deck joints and sealing cracks in the deck surface. It was deemed to be more cost efficient to modify the existing contract than to bid this part of the work. The effort...