File #: 1284-2018    Version: 1
Type: Ordinance Status: Passed
File created: 4/30/2018 In control: Recreation & Parks Committee
On agenda: 6/11/2018 Final action: 6/13/2018
Title: To authorize the Director of Recreation and Parks to enter into contract with Tyevco, Inc. for improvements to Audubon Park; to authorize the transfer of $81,394.00 between projects within Recreation and Parks Bond Fund; to amend the 2018 Capital Improvements Budget; to authorize the expenditure of $301,394.00 from the Recreation and Parks Voted Bond Fund; and to declare an emergency. ($301,394.00)
Attachments: 1. Audubon Park Improvements 2018 - DAX
Explanation

Background: This ordinance authorizes the Director of the Recreation and Parks Department to enter into contract with Tyevco, Inc. for improvements to Audubon Park.

Audubon Park is a 7.35 Acre Park located between Hudson Street and Weber Road, East of I-71. This project will provide a new loop path, replacement of basketball court, and new playground, as well as associated storm water improvements for the park. These improvements will serve residents of the North Linden Area by providing a needed and easily accessible neighborhood recreation space.

Bids were advertised through Vendor Services, in accordance with City Code Section 329, and received by the Recreation and Parks Department on April 26, 2018. Bids were received from the following companies:

Company Status Amount
Tyevco, Inc. (MAJ) $276,394.00
M&D Blacktop (MAJ) $375,000.00

After reviewing the proposals that were submitted, it was determined that Tyevco, Inc. was the lowest and most responsive bidder.

Tyevco, Inc. and all proposed subcontractors have met code requirements with respect to pre-qualification, pursuant to relevant sections of Columbus City Code Chapter 329.

Principal Parties:
Tyevco, Inc.
1678 West Audubon Blvd.
Lancaster OH 43130
James Boggess, 614-265-6477
CC#: 31-1626034

Fiscal Impact: Ordinance 0154-2018 authorized the acceptance and appropriation of a grant, in the amount of $75,017.00, and a grant match, in the amount of $144,983.00, for this project. This ordinance will authorize additional grant match funds, in the amount of $81,394.00. The additional matching funds will create a new total of $301,394.00 in funding for this project. $301,394.00 is budgeted and available in the Recreation and Parks Grant Fund 2283 and Voted Bond Fund 7702 to meet the financial obligations of this contract.

Emergency Justification: An emergency is being requested in order for work to begin during the summer season and allow the work to be complete prior to the...