header-left
File #: 1650-2017    Version: 1
Type: Ordinance Status: Passed
File created: 6/14/2017 In control: Public Utilities Committee
On agenda: 7/31/2017 Final action: 8/3/2017
Title: To authorize the Directors of Public Utilities and Public Service to enter into a Construction Administration and Construction Inspection (CA/CI) services agreement with DLZ of Ohio, Inc.; to authorize the appropriation and transfer of $224,755.39 from the Sanitary Sewer Reserve Fund to the Sanitary Sewer General Obligation (G.O.) Bond Fund; the transfer within of $324,243.26 from Sanitary Sewer G.O. Bond Fund and a total expenditure of up to $548,998.65 from the said fund; to authorize the transfer within and the expenditure of up to $248,022.24 from the Department of Public Service Streets and Highways Bond Fund; to amend the 2017 Capital Improvements Budget; and declare an emergency. ($797,020.89)
Attachments: 1. Ord 1650-2017 DLZ template Director's Legislation Info Sheet, 2. Ord 1650-2017 530161-100105 Schedule 2A-1 (SWIF) (650600-100010), 3. Ord 1650-2017 650870.3 Schedule 2A-1 (SWIF), 4. Ord. 1650-2017 Funding Template REVISED MJC
Explanation

1. BACKGROUND: This legislation authorizes the Directors of Public Utilities and Public Service to enter into a Construction Administration and Construction Inspection (CA/CI) services contract with DLZ of Ohio, Inc. The services for this contract include oversight of projects during construction to ensure that work performed by the construction contractor conforms to project plans and specifications. DLZ of Ohio, Inc. will perform construction administration/inspection services for Division of Sewerage and Drainage that commence construction during the years 2017 through 2019. The contract will be modified as needed throughout the three (3) year period to include these projects as they go to construction. Projects are located throughout the City of Columbus.

This group of CA/CI projects consists of funding for two (2) Sewerage and Drainage projects and one (1) Division of Public Service.

Division of Sewerage and Drainage:
General CA/CI (DPU) CIP #:650800-100000 $: 50,000.00
Morse/Dominion Integrated Solutions (DPU) CIP #:650870-100003 $: 498,998.65
DPU EXPENDITURE: $: 548,998.65

Roadway Improvements - Cannon Drive* (DPS) CIP #:530161-100105 $: 248,022.24

TOTAL EXPENDITURE: $ 797,020.89

*: The Department of Public Service is funding the CA/CI portion of the relocation of Cannon Drive on the Ohio State University Campus. The Franklin Main Sewer is located within Cannon Drive and it will be relocated as a result of the Cannon Drive Relocation Project.

2. BID INFORMATION: The Department of Public Utilities advertised for a RFP for Construction Administration / Construction Inspection (CA/CI) services on the City’s Vendor Services website per the overall provisions of Section 329. Four (4) proposals were received on November 4, 2016 from: PRIME AE Group, DLZ Ohio, Stantec Consulting Services, and CTL Engineering.
The Department of Public Utilities recommended that three-year agreements be awarded to each of...

Click here for full text